...SIX SIGMA MANUFACTURING CASE STUDIES
..
Listed below are a few of the Six Sigma projects carried out by our customers:
 
Company Name: Sudarshan Chemical Industries Ltd., a leading pigment manufacturing company.
 
Project Objective: Increase plant manufacturing capacity for a specified pigment from 60 tons per month to 90 tons per month.
 
Effort: 8 persons for 6 months.
 
Project Result: Production increased to 87 tons per month, an increase of nearly 50%, achieved through efficient utilization of existing process, optimization of process parameters and removal of production bottlenecks and standardization. This resulted in 100% increase in profitability, and nearly 50% increase in sales value.
 
  sixsigmadss.com Training Calendar
  ...
  sixsigmadss.com Highlights
   

 
Financial Benefits: Financial impact of this is savings of Rs 2.3 million per annum.
 
Next Steps: It is proposed that a full blown Six Sigma deployment is undertaken. Initiation of Green Belt training and projects can help the company get full advantage of the initial success.
Reduce incoming raw material inspection and testing cost by 20%
Improvement in overall plant production
Improvement in vendor scheduling process
Reduction in new product development and commercialization cycle time
Improvement in plant yield
Reduction in energy cost by 20%


 
Company Name: Bharat Forge Limited, a world leader in manufacture of forgings and supplier of machined automotive components to world leaders like Spicer, Meritor, Mercedes Benz, Toyota etc.
 
Project Objective: Reduction in rejection of crankshafts for a particular export line from 4% by 2%.
 
Effort: 2 persons for 6 months.
 
Project Result: On starting the project, it became apparent that the prevailing rejection was actually 5.9% (not 4%), thus increasing the challenge. On completion of the project the rejection dropped from 5.9% to 3.2% in six months. Average production level of this production line being 6300 crankshafts per month, it means a reduction in rejection of 170 crankshafts per month. As a result, rework reduced and productivity increased.
 
Financial Benefits: Financial impact of this is savings of Rs 2.3 million per annum.
 
Next Steps: It is proposed that a full blown Six Sigma deployment is undertaken. Initiation of Green Belt training and projects can help the company get full advantage of the initial success.

................